The Parliamentary Committee on Local Government and Community Affairs has raised concerns over revenue compliance among mining companies operating in Moyamba District after learning that only six of the 21 companies operating in the district are reportedly making payments to the Moyamba District Council.

The disclosure was made during the Committee’s oversight visit to the Council on Thursday, November 12, 2026, where Members of Parliament assessed the Council’s performance in revenue mobilization, infrastructure development, financial management and the delivery of devolved services.

The revelation prompted concerns among Committee members, who questioned why the remaining 15 mining companies were reportedly not contributing to the Council’s revenue base.

The Committee Chairman assured the Council that Parliament would follow up on the matter, including considering inviting the companies concerned to explain their positions and clarify any exemptions they might be claiming.

The Committee also urged the Council to strengthen its engagement with mining companies and other businesses to improve revenue collection and generate more funds for local development.

On revenue mobilization, the Council identified property rates, business licences, mining-related payments and other local charges as its main sources of internally generated revenue. However, Council officials acknowledged that existing collection arrangements, particularly the escrow account system, were not functioning effectively.

The Council disclosed that it had engaged Paramount Chiefs, traditional authorities and private revenue collectors to improve revenue collection, particularly in Moyamba Township and Moyamba Junction, with plans to extend the exercise to Tiama and Mukundi.

Beyond revenue mobilization, the Committee examined the Council’s expenditure, particularly its annual surgical support programme, which provides assistance to approximately 150 vulnerable residents.

Committee members questioned the programme’s sustainability, cost-effectiveness and accountability, recommending a comprehensive review to establish its overall expenditure, beneficiaries and impact. They stressed that operational costs should be reduced wherever possible without compromising the number of beneficiaries or the quality of healthcare services.

Civil society representatives at the engagement also called for stronger beneficiary screening, proper documentation and effective monitoring. They argued that resources spent on the programme over the years could also have been used to improve schools and health facilities.

The Council’s Finance Officer reported that internally generated revenue had supported several interventions, including healthcare activities, the rehabilitation of the mini-stadium, guesthouse and staff quarters, the procurement of a vehicle for revenue mobilization and support to selected primary healthcare facilities.

The Committee also received updates on infrastructure projects, including feeder road maintenance, bridge construction and drainage works.

However, the Council’s Engineer raised concerns over alleged interference by Fujian Jincheng Mining Company during the construction of rectangular cross culverts. He alleged that the company’s mining activities repeatedly obstructed construction works by filling excavated areas with mining materials, resulting in the destruction of approximately 100 bags of cement.

According to the Engineer, the contractor was eventually forced to withdraw workers and equipment from the site. He added that although the Council’s Legal Officer had written to the company, the matter remained unresolved.

The Engineer further identified inadequate funding from the Road Maintenance Fund Administration (RMFA) as a major challenge, noting that available allocations were insufficient to address the district’s extensive feeder road network.

On projects being implemented under the World Bank-supported Accountable Governance for Basic Service Delivery Project, the Council reported that the Community Health Post at Gundama was approximately 85 per cent complete, while the primary school project at UMC had reached 71 per cent completion.

The Committee emphasised the need for all projects to be completed in accordance with approved designs, specifications and quality standards.

Education was another major area of concern during the engagement. The sector representative disclosed that some primary schools outside Moyamba Township had only one teacher responsible for teaching pupils across multiple classes.

He further revealed that the district had approximately 670 schools across 14 chiefdoms but only six School Quality Assurance Officers responsible for monitoring educational standards.

Additionally, only 15 of the district’s 23 senior secondary schools had uploaded the required information under the government’s education data management requirements, while efforts were ongoing to support the remaining eight schools.

The representative also cited delayed disbursement of grants, rising fuel costs and disruptions associated with ongoing national census activities as challenges affecting school monitoring and teaching.

The Committee acknowledged these concerns and indicated that its findings on education would be shared with the Parliamentary Committee on Basic and Senior Secondary Education for further engagement.

Other institutional challenges highlighted during the visit included inadequate technical personnel, limited mobility for project supervision and concerns over the conditions of service of local council employees.

In its observations, the Committee identified weak revenue mobilization, reported non-compliance by mining companies, inadequate infrastructure funding, staff shortages and weaknesses in financial accountability as major challenges requiring urgent attention.

It also expressed concern that perceived capacity and accountability weaknesses among local councils could undermine the confidence of development partners and government institutions in entrusting them with substantial financial resources.

The Committee recommended stronger revenue collection mechanisms, improved financial documentation, a comprehensive review of the surgical support programme and increased engagement with companies operating within the district.

It further urged the Council to demonstrate transparency, sound financial management and institutional competence to strengthen public confidence and improve service delivery.

The oversight visit forms part of Parliament’s broader responsibility to monitor local government institutions, assess the implementation of devolved services and ensure that public resources are effectively utilized for the benefit of citizens.

 

 

0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments